The next step is to enter separate tasks into the project planner software with times associated with each. The software is set up to respect weekends and holidays and will move a task to the following day if one over-allocates someone on a day. One can also ask the software to level resources automatically – and it will so no one is working 14 hours while everyone else is working five. Note that there are a number of tasks throughout the steps that have no hours assigned to them. These are milestones – markers in the.