A survey in the resource-constrained project and multi-project scheduling problems

This paper surveys studies of RCPSPs and RCMPSPs under consideration of four categories of project activities, simply recorded as categories A, B, C, and D. Category A refers to activities can be performed using fixed resources along The Y-axis over fixed durations along The X-axis, and cannot be interrupted | A survey in the resource-constrained project and multi-project scheduling problems Journal of Project Management 5 2020 117 138 Contents lists available at GrowingScience Journal of Project Management homepage A survey in the resource-constrained project and multi-project scheduling problems Samer Ben Issaa and Yiliu Tua a Schulich School of Engineering Department of Mechanical and Manufacturing Engineering University of Calgary Canada CHRONICLE ABSTRACT Article history Resource-Constrained Project and Multi-Project Scheduling Problems RCPSPs and Received September 20 2019 RCMPSPs have been essential topics of study over the last three decades. Both problems Received in revised format Oc- consist of activities that must be scheduled subject to precedence and resource constraints. tober 2 2019 This paper surveys studies of RCPSPs and RCMPSPs under consideration of four categories Accepted November 14 2019 Available online of project activities simply recorded as categories A B C and D. Category A refers to November 14 2019 activities can be performed using fixed resources along The Y-axis over fixed durations Keywords along The X-axis and cannot be interrupted. Category B applies to activities that can be Project scheduling performed using the same type of resource in category A but can be interrupted. Category C ABCD activity classifications refers to activities that can be performed using flexible resources over flexible durations and Limited resources cannot be interrupted. Category D refers to activities can be performed using flexible re- sources over flexible durations and can be interrupted. Many algorithms have been devel- oped to solve the RCPSPs and RCMPSPs when activities are classified individually under category A B or C. However in practice welding cutting or assembly activities in a man- ufacturing projects for an oil cargo can be under a new category so-called D. The project manager can speed up or slow down these activities

Không thể tạo bản xem trước, hãy bấm tải xuống
TÀI LIỆU MỚI ĐĂNG
15    15    4    25-11-2024
Đã phát hiện trình chặn quảng cáo AdBlock
Trang web này phụ thuộc vào doanh thu từ số lần hiển thị quảng cáo để tồn tại. Vui lòng tắt trình chặn quảng cáo của bạn hoặc tạm dừng tính năng chặn quảng cáo cho trang web này.