A probabilistic model is proposed to predict the risk effects on time and cost of public building projects. The research goal is to utilize a real history data in estimating project cost and duration. The model results can be used to adjust floats and budgets of the planning schedule before project commencement. Statistical regression models and sample tests are developed using real data of 113 public projects. The model outputs can be used by project managers in the planning phase to validate the schedule critical path time and project budget. |