This paper presents the geotechnical conditions, the ground improvement methodologyand quality control during construction. The control sequence is performed by vertical and then horizontal drilling holes. The method of control work after excavation (horizontal control) allows to confirm the quality of the treatment blocks and specifically the bonding between the treatment block and the diaphragm wall. |